GUINEA BISSAU

Community Projects (CP) & Institutional Supports (IS) Monitoring Summary

 

CP 10:             Capacity building and improvement of fishing equipment for Sonaco fishery communities

 

Objective: To ensure the regularity of fish distribution through the improvement of fishermen equipment and capacity building of Sonaco community

Duration:             24 monts, starting in April 2001

Beneficiaries: Members of the fishermen Association of Sonaco

Budget:             US$ 17,750 (Contribution of beneficiaries: 11%)

What aspect of policy dialogue the project sets out to inform: Responsible utilization of fish products (article 6.7 of CCRF).

Available information on progress: The activities are ongoing. No further report available.